Gantt Chart

Pro

Dates computed from dependencies, with the critical path and the float drawn.

Float

Shipping one release

Twelve tasks, dependencies, and the path that sets the date

day 0day 5day 10day 15day 20day 25todaySpec the APIDesign passServer routesBuild the UIWrite the docsTest suiteAccessibility auditPerformance passFix what they findRelease notesPackage and signShip it
28 days end to endcritical, 8 of 12 tasksfloat

Twenty eight days end to end. 8 of the twelve tasks are on the critical path; the docs have 13 days of float. The critical path is Spec the API, then Design pass, then Build the UI, then Test suite, then Fix what they find, then Release notes, then Package and sign, then Ship it. Arrow keys move between tasks and Escape clears the selection. Every task follows as a table.

Release plan of twelve tasks with dependencies and the critical path
TaskStartsEndsDaysFloatWaits for
Spec the APIday 0day 33none, criticalnothing
Design passday 3day 85none, criticalSpec the API
Server routesday 3day 741Spec the API
Build the UIday 8day 168none, criticalDesign pass, Server routes
Write the docsday 8day 12413Design pass
Test suiteday 16day 215none, criticalBuild the UI
Accessibility auditday 16day 1932Build the UI
Performance passday 16day 1932Build the UI
Fix what they findday 21day 254none, criticalTest suite, Accessibility audit, Performance pass
Release notesday 25day 272none, criticalWrite the docs, Fix what they find
Package and signday 25day 272none, criticalFix what they find
Ship itday 27day 281none, criticalRelease notes, Package and sign

Nothing here was placed by hand: every date comes from a duration and a list of what a task waits for. 28 days end to end, and 4 of the twelve tasks could slip without moving that, one of them by 13 days. Turn the float off and the plan looks like twelve equally urgent bars, which is how most Gantt charts are drawn and the reason they are not much use. This is also the difference from the resource scheduler, where blocks are dragged to where a person decides they go.

This component installs from the private registry, which opens with Pro. The command and the one-time setup are shown here once your licence key is in this browser.

6 sections, and every other premium component

The preview above is the real Gantt Chart, running. One purchase opens the sections above on this page and on every other component in the library.